30.1 Contingent receivables

As at the reporting date, PGE Group held PLN 72 million in contingent receivables related to a potential refund of excess excise duty. The Group is waiting for a ruling by the Supreme Administrative Court on what excise duty rate should be applied in settling the excise duty relief related to the redemption of property rights created in renewable energy sources prior to January 1, 2019.

According to PGE Group, this relief should be settled using the rate applicable at the time the electricity generated from renewable sources is sold to the end customer, i.e. 20 PLN/MWh. This was confirmed in a ruling by the Voivodship Administrative Court in Rzeszów of October 8, 2019.

The tax authority issued a cassation appeal against this ruling by the Voivodship Administrative Court on November 20, 2019.